Eliminate day 1
- Dust extractor fans installed
- Drop cloths cover your floors
- Toilets, sink, bathtub, faucets, mirrors, lighting, etc are removed & water pipes are capped
- Old, moldy gyproc, cement & tiles are removed & hauled away
- Electrician installs new wiring, electrical boxes, exterior fan, lighting & plugs to your specifications
- Vacuuming & clean up
- Wayne inspects all merchandise & brings in construction materials
- All this in a manner that assures your continuing comfort & use of your home
|
Resurrection day 2
- Install T & G plywood floor
- A drywall ceiling is put up
We install insulation & a vapor barrier to eliminate moisture, rot & bacteria
- Installation of plumbing for bathtub, sink,shower & toilet
- A concrete base is prepared to receive & hold your bathtub
- The bathtub is installed level
- Waterproof drywall is installed around bathtub & shower enclosures
- Durabond & drywall taping is applied to walls & ceiling
- Clean up & vacuuming
|
Metamorphosis day 3
- Ceiling fan is vented to exterior
- Durabond is scraped smooth
- Plaster is smoothly applied over the durabond surfaces
- To guarantee straight & even lines, we analyze the layout of your ceramic tiles
- Waterproof wall glue is applied & your redecoration begins
- Ceramic tiles are started level around the bathtub & flow to the balance of the room
- Epoxy cement is spread on the floor & the ceramic tiles are laid to match the wall tile layout
- Marble door sills are installed
|
Jubilation day 4
- The walls & ceiling are sanded
- Ceramic wall & floor tiles are thoroughly cleaned
- Mildew-resistant grout is applied to joints in matching colors
- The vanity unit, sink, faucets & mirrors are installed
- The toilet is installed
- Towel bars, toilet paper, soap & toothbrush holders & other accessories are mounted
- A colored silicone is applied around the bathtub enclosure
- Tools & equipment are packed
- Your new bathroom awaits you
|